45Hospital ~ Hôpital <> Hurdman & N Rideau · preliminary, to Oct 31
Route 45 · October 2026 · Preliminary, figures to Oct 31
90.4% on time so far, 18 of 139 all-day routes.90.4% on time so far.
18 of 139 all-day routesTarget 85%
Did not runᓱᓕ ᐅᒃᑐᖅᑕᐅᓯᒪᙱᑦᑐᖅ
unchanged from September
28 of 31 measured days met the 85% target.
ᐊᑐᖅᑎᑦ ᐱᕕᖏᑦ ᐊᓯᐅᔪᑦ: ᓱᓕ ᐅᒃᑐᖅᑕᐅᓯᒪᙱᑦᑐᖅ
Target 85%
A for 3 months in a row (3 shown).Month by month
A for 3 months in a row (3 shown). All bars in the 90 to 100 band; October outlined.
- Aug 93.3%
- Sep 90%
- Oct 90.4%
Bottom of the table, October
The 139 ranked all-day routes, by share on time
What changed in October
Not measured yet.
Riders said
Not measured yet.
Take this month with you
- Download this monthCSV of the network report, October 2026CSV ᑎᑎᖅᑲᖅ
- Share this monthWith the month’s social card
- ᑕᖅᑭᖅ ᐊᓂᒍᖅᑐᖅSeptember 2026 · 90% · A September
- ᑕᖅᑭᖅ ᖃᐃᔪᖅNovember starts Sunday